HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Actual operation steps for starting, stopping, and switching the new hydrogen compressor...

2018-04-08View Original

Thread Content

The last edit to this post was made by Green Lotus on 2018-4-8 at 22:05. Actual steps for starting, stopping, and switching the new hydrogen compressor: To start the compressor, after all preparations are complete: 1. Start the compressor under no-load conditions. 2. Open the compressor’s outlet. 3. Apply a 50% load. 4. Open the compressor’s inlet. 5. Apply a 100% load
Reply #22018-04-08
It’s always included in the workshop operating procedures.
Reply #32018-04-09
Add me on QQ, 356109854, and I’ll send it to you
Reply #42018-04-09
To be honest, the design of this “new hydrogen compressor” still needs to be determined; there are various types of hydrogen compressors, and the steps you propose may not be suitable for every type of equipment. What was said above is correct; it is necessary to follow the operating procedures strictly, and actions should be taken based on sound reasoning. If it is found that something does not conform to these procedures, a report should be submitted to obtain approval from superiors. Only after the procedures are modified can operations be carried out in accordance with them. Working with hydrogen requires caution; one cannot be reckless, and as some experts say, it is you who will end up hurt in the event of an accident. Is there a principle behind this? It’s better to clarify that principle and then improve the operating procedures step by step, according to different levels.
Reply #52018-04-10
Let me tell you about our procedures for your reference! We are a two-stage compression reciprocating machine; once the startup conditions are met, 1) establish the flow path by closing the inlet valve and fully opening stage 1 inlet and outlet valves as well as stage 2 inlet and outlet valves ; 2. Start the machine with no load. 3. Once all operational parameters such as temperature and vibration are within acceptable limits, fully open the inlet valve. 4. Increase the load to 25%, 50%, 75%, and 100%. 5. Adjust the outlet pressure to match the system pressure using the first, second, and third control valves, then open the outlet valve to integrate the system. (When the unit first started operating, both the inlet and outlet valves were kept fully open; it was only after one of the outlet check valves failed that this operation method was adopted.) )

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.