When was catalyst drying completed?

2018-04-08View Original

Thread Content

When is catalyst drying completed for the first start-up of the unit, in order to save start-up time?
Reply #22018-04-08
After the high-pressure airtightness test of nitrogen was completed without any issues, the catalyst was loaded and dried. After drying is complete, perform high-pressure hydrogen leak testing. It’s relatively coherent.
Reply #32018-04-08
Once the catalyst has been loaded and the airtightness test with high-pressure nitrogen is successful, drying can begin
Reply #42018-04-10
Once airtightness is ensured, we can proceed, right?
Reply #52018-04-19
After the system achieves gas-tightness, the system is heated to dry the catalyst
Reply #62018-04-19
Once the nitrogen airtightness test is completed, the catalyst can be dried.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.