Seek help: The recycle hydrogen coalescer is severely contaminated with water after gasoline hydrodesulfurization and cooling

2019-06-26View Original

Thread Content

As the title suggests, the normal temperature at low load is 40 degrees. The coalescer contains little oil and mostly water; it needs to be drained several times a day. Please help solve this issue
Reply #22019-06-27
Are there any abnormalities in the level and fluid level? Take a sample after the cold high-pressure valve to see if there is much water present Is the liquid level set too high? Try lowering it to 45-50 and see. At this temperature and pressure, there shouldn’t be this much water. Is the circulation air volume larger than before?
Reply #32019-06-27
The temperature and pressure are low, and the levels of the liquid in the system are normal. What’s strange is that most of it is water, with very little oil. We tried reducing the amount of circulating hydrogen before, but the problem of water contamination persisted; however, the hydrogen-to-oil ratio was much higher than the designed value. It’s odd that there’s no oil present, only water
Reply #42019-06-27
After the low-pressure section is the circulating hydrogen coalescer; there is no heat exchanger
Reply #52019-06-27
Was the water sample that was removed analyzed? Is there a desulfurization process later on? Analyze the water sample to take a look.
Reply #62019-06-27
No analysis has been done yet; the next step is the circulating hydrogen desulfurization tower
Reply #72019-06-30
Have the water injection lines and steam lines from the previous process stages been checked?
Reply #82019-07-06
The inside of the cold low-temperature section should be checked
Reply #92019-07-07
You can try lowering the temperature a bit; it’s normal for some water vapor to be carried away before it can be separated due to the high circulation rate.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.