How is temperature control achieved according to the heating curve during the furnace drying stage of a sulfur recovery unit?

2017-06-05View Original

Thread Content

This post was last edited by liaifeng on 2018-9-3 08:58. How can temperature control be achieved according to the heating curve during the furnace heating stage of the sulfur recovery unit? Use a higher temperature as the control benchmark?
Reply #22017-06-07
It is impossible to match the furnace drying curve exactly during drying, especially in the low-temperature stage. It is ideal if the pilot light device provided by the burner supplier has the function of drying out the furnace in the low-temperature stage; otherwise, once the main burner is activated, the temperature may skip the low-temperature stage and go straight to the second constant-temperature stage.
Reply #32017-06-12
During the first heating cycle of sulfur, the heating curve must be provided by the manufacturer of the furnace lining. Generally, there are constant temperature stages at 110°C, 350°C, 550°C, and 850°C. The low-temperature stage of heating is relatively difficult to control. At a constant temperature of 110°C, it is possible to avoid turning on the furnace and use the hot air coming from the fan; if an air preheater is available, it can be utilized; In the constant-temperature section at 350°C, it is possible to make use of the burner’s pilot light; some units are equipped with specialized heating nozzles for low-temperature zones that can reach temperatures up to 500°C℃ ; It’s easier to control at temperatures above 500°C.
Reply #42018-09-03
Here, we use air heaters to maintain the temperature in the low-temperature section (heated with 1.0 Mpa steam).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.