What materials are needed for the planning approval of a project?
Reply #22017-01-08
Take Shanghai as an example. The approval process for construction projects in Shanghai is as follows: First, a project feasibility report is prepared and submitted to the Development and Reform Commission, the Construction Commission, and the Planning Commission. The design institute then creates the design plans and construction drawings. Subsequently, the Planning and Land Resources Bureau approves the project. After obtaining approvals from departments such as those responsible for environmental protection, health, water resources, landscaping, and traffic control, a planning permit can be obtained. The land use permit and related land acquisition procedures are then submitted to the quality inspection station to obtain the construction permit. Once that is done, the construction procedures become much simpler. A detailed flowchart is available. What approvals are required for project construction? The process involves all procedures from the initiation of a construction project to its completion (including approval for project initiation, planning and design, submission of applications for construction projects, and completion inspection of such projects). I. Approval for project initiation 1. One original copy of the project initiation application form. 2. One copy of the project proposal or feasibility study report. 3. One copy of the document confirming ownership of the land to be used for the project, or an opinion letter regarding the preliminary review of that land. 4. One copy of the estimated investment cost for the project. 5. One original copy of a financial certification issued by a banking or financial institution. 6. One copy of the duplicate of the business license of the legal entity in question ; (Real estate projects require one copy of a qualification certificate.) 7. Project topographic map (one copy). 8. Opinions from relevant functional departments. II. Planning and Design 1. The Municipal Planning Bureau issues the red line for survey and design based on the overall urban plan and the project approval documents, providing the conditions for planning and design. 2. Architectural design is divided into three stages, namely conceptual design, preliminary design, and construction design. 3. City. The approval process for capital construction projects involves the Planning Commission, Planning Bureau, Construction Bureau, fire department, environmental protection agency, energy conservation department, landscaping department, urban management department, epidemic prevention department, drawing review authorities, place name registration office, price control bureau, housing management bureau, power supply authority, as well as water and gas companies. Every local construction bureau has a flowchart showing the approval process; some even provide free brochures on this topic. I suggest you get one from the construction bureau and another from the planning office. Once you have these brochures outlining the procedures, and once you understand the terminology used in them, you’ll be an expert at handling the necessary formalities for any project. Approval procedures for project construction: Project proposal → Approval or approval after expert discussion → Preparation of a feasibility study plan → Submission to the development and reform department for approval → Preparation of an environmental impact assessment report → Submission to the environmental protection department for approval → Design of the building plan → Presentation to authorities for approval → Preparation of construction drawings. Obtaining a land certificate from the land department (either through sale or allocation) → Going to the planning department to obtain a site selection approval letter → Going to the land department to get approval for the use of land for construction → After the building plan is approved → Going to the planning department to obtain approval for the building plan and a construction permit → Going to the land department to get the final approval for land use → After the construction drawings are ready → Going to the planning department to obtain a construction permit. The following documents are required during this process: 1. A map showing the boundaries of the land (to be prepared by the planning department or a surveying agency); 2. Up-to-date topographic maps at a scale of 1:500–1:2000 (in CAD format).
Reply #32017-01-08
This also knows: victory:
Reply #42017-01-09
It varies from place to place, but it’s more or less the same.
Reply #52017-01-09
The local management committee will take care of everything for you. Otherwise, it will be very difficult to get permits later on. Three simultaneities
Reply #62017-01-11
Handling planning specifically means obtaining a construction project planning permit. The main documents required include proof of project approval, application report, land title and use permit, five sets of drawings prepared by the design institute (current condition, general layout, vertical planning, landscaping, and comprehensive utility networks), as well as floor, elevation, and section views of the individual buildings. In some cases, aerial views of the project, as well as approvals for safety and environmental assessments, are also required.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.