I would like to consult fellow sailors regarding the submission of documents related to technical defects and the issues of responsibility

2017-03-24View Original

Thread Content

The contractor was responsible for both the design and construction; the design drawings were submitted to the owner in accordance with the contract. During the construction process, due to obvious technical defects in the design drawings, the quality of the work became substandard. May I ask: Does the property owner have the responsibility to detect defects, and is they liable?
Reply #22017-03-24
Is there any provision in your contract regarding our audit responsibilities? Is quality assurance the responsibility of the contractor, as specified in the contract?
Reply #32017-04-21
Since it is E+C (assuming procurement P is not included), the responsible party is the contractor.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.