What needs to be completed before the design phase of a chemical engineering construction project begins?

2017-09-29View Original

Thread Content

We have a small chemical engineering project, and the design kickoff meeting is about to take place. What preparations need to be made by us as the client, and what tasks does the design firm need to complete first?
Reply #22017-09-29
The owner prepares the funds, and the design institute prepares the drawings. You need to go through the procedures for launching each part of the project
Reply #32017-10-19
The design institute proposes the \"Design Coordination Procedure\", the project schedule, and a list of professionals in the project team, while issuing unified design regulations; Party A: Confirm the project scope and design basis conditions ; Design depth requirements ; Confirmation of the factory’s general layout plan and key equipment data sheets.
Reply #42017-11-15
The owner is responsible for completing the procedures related to project approval and registration, land use, planning, environmental impact assessment, safety assessment, and waste discharge

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.