Hello, fellow engineers. This is my first time working on an EPC turnkey project. I am a pipeline engineer, and I would like to ask everyone how to fill out the project communication form: 1. Should the recipient field be filled in with our design institute, or with the project owner?; 2. Sign-off opinions: who needs to sign them ; 3. For example, in the case of design issues, are the comments from the review process provided to the designers only after they have been completed, so that they can submit their responses? If anyone has a more detailed procedure for handling this, I would be very grateful if experts could share it!
You can find the \"Project Coordination Procedure\" in the \"Project Procedure Manual\" or the \"Uniform Project Regulations\"; this procedure will contain the answers you need.
1. Service: The construction entity; All parties involved in the project sign off; 2. Design-related issues are first discussed and agreed upon before a design response is provided; 3. After the design response is prepared, it must be approved by the project owner before it can be issued ; The above are merely personal opinions; I hope they are helpful to you.
What you say makes sense; it can be closed. Since our C section was subcontracted out, the construction company submitted an engineering liaison form to us; the recipient listed on that form was our engineering company. We then changed the recipient and sent the form back to the construction company. So how should we respond to the construction company?
Specify the construction unit and the general contractor as the two recipients