Which comes first, fire safety approval or construction permits?

2018-04-17View Original

Thread Content

For an industrial plant project, one needs to go to the service desk to obtain fire safety approvals and a construction permit. The fire department of the public security bureau said: Bring the project’s construction permit! So, carrying a pile of documents, I went to the Construction Bureau’s counter to apply for a construction permit. After reviewing the documents, the clerk asked, \"Where is the fire safety approval for your project?\" How can a construction permit be obtained without fire safety approval? I’m confused – which comes first, the fire safety approval or the construction permit?
Reply #22018-04-17
First, conduct the fire protection design review. Fire safety is part of safe construction and quality supervision, and safe construction and quality supervision are part of obtaining a construction permit; therefore, it is necessary to handle fire safety matters first in order to get the construction permit.
Reply #32018-04-17
It is recommended that the relevant departments conduct further investigation; it might be intentional, and further study is needed (regarding tobacco and alcohol).
Reply #42018-04-17
Oh, one must study the policies carefully, understand the regulations, and also remain grounded in reality.
Reply #52018-04-18
Let me tell you quietly: there are rules in this line of work, and you need to understand that.
Reply #62018-04-18
Thanks, bro. If someone comes from another province to invite you to drink Hongmao liquor, be sure to save some for me; I’ll drink it with you.
Reply #72018-06-03
For a legitimate project, the design institute must first prepare a feasibility study report (which will require assessments related to the environment, energy use, noise levels, and occupational health and safety). Only after this report is discussed and approved can the application be submitted for one of the five permits and one document required for project implementation, namely the construction permit.
Reply #82018-06-03
The feasibility study report does not include environmental impact assessment, energy assessment, noise assessment, or occupational health assessments; these need to be prepared by separate third-party consulting firms.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.