It is planned to use the existing equipment to produce a few new varieties without adding any additional devices. What procedures are required for feasibility studies, energy savings, safety, environmental protection, etc.? PS, according to Order No. 41 on work safety, safety requirements only require a \"special safety assessment\" before applying for a change to the work safety license.
Is it necessary to follow the procedures for technical improvement projects?
The procedures for technical renovation projects need to be followed: first, register the project at the relevant window in the local government office’s economic planning department. Then, entrust a third party to prepare an environmental impact assessment report, and use the registration number issued by the economic planning department to submit the report to the environmental protection agency. Once the environmental impact assessment is approved (currently, wastewater and exhaust gas are subject to self-inspection), the necessary procedures for project construction can be carried out. Since the project makes use of existing equipment without adding any new facilities, it is advisable to consult local departments such as those responsible for planning, quality supervision, and special inspections to determine whether approval is required As for safety assessments, job evaluations, capability assessments, total pollution indicators, fire safety, and so on, it’s likely that none of these procedures can be skipped.