Thread Content
This post was last edited by Zhi Zhe Ming on 2017-12-24 10:13 At 10 a.m. on December 13, the No. 2 propylene tower, the largest equipment of the 1.4 million tons/year ethylene unit of the 40 million tons/year refining and chemical integration project of Zhejiang Petrochemical Company, which was general contracted by Sinopec Refining and Chemical Company Shijian Company, was successfully hoisted into place. @Fish in the desert
Previously, the propylene tower was delivered to the site on November 13. Zhejiang Petrochemical’s largest propylene tower is shipped to the site. Is it 1,800 tons or 1,500 tons? https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=1873963 (Source: Haichuan Chemical Forum Network)
For more than a month, the Zhejiang Petrochemical Ethylene Project Branch of the First Installation Branch of Sinopec No. 10 Construction Company, which is responsible for the installation and construction, has been carrying out modular assembly of propylene towers on the ground.
Sinopec Heavy Lifting and Transportation Engineering Co., Ltd. and Xugong Group are also actively carrying out crane assembly, commissioning and hoisting preparations. This hoisting will use the second XGC88000 4000-ton crawler crane made by XCMG Group and the XGC16000 1250-ton crawler crane made by XCMG China.
This hoisting uses the XGC88000 4,000-ton crawler crane for main lift + XGC16000 1,250-ton crawler crane for slip-tail delivery. The main hoisting 4,000-ton crawler crane has a 102-meter main boom + a 27-meter jib working condition. The diameter of the 2# propylene distillation tower is nearly 8 meters, the erection height reaches 110 meters, and the main crane lifting weight reaches 1914 tons. The picture shows the scene when the hoisting is ready.
This post was last edited by Zhizhe Ming on 2017-12-25 10:27 At 7:17 in the morning, the commander-in-chief Hu Guoxiang gave the order and the hoisting began.
Second station? So where did the first 4,000-ton crawler crane go?
This post was last edited by Wise Ming on 2017-12-24 09:59. Hoisting is in progress, and the 1,250-ton crane slipping behind looks so small.
This post was last edited by Wise Ming on 2017-12-24 11:34. Finally, here is a panoramic view after hoisting.