Does anyone know about the construction status of Henan's first 200,000 tons/year dimethyl ether and Yongmei Group's 100,000 tons/year polyformaldehyde?

2009-06-10View Original

Thread Content

For example, has the project started construction? Which design company designed it?
Reply #22009-06-10
Henan Capital Chemical Technology Co., Ltd. is located in Xiangcheng County Coal Coking Circular Economy Industrial Park. It is a coal chemical enterprise controlled by Pingmei Group. The company plans to invest 500 million yuan to build a 200,000-ton dimethyl ether project. The project mainly uses the coke oven exhaust gas of Shoushan Coking Co., Ltd. to produce dimethyl ether. At present, the project is progressing smoothly. The civil engineering work is under intense construction. The main equipment has been ordered. The desulfurization tower, gas cabinet and refrigeration station are under construction. The rough desulfurization system has entered the installation stage, and the sewage treatment plant equipment has been installed. After the project is completed and put into operation, it will achieve an annual output value of 900 million yuan and profits and taxes of 180 million yuan.
Reply #32009-06-18
Yongmei Group's 100,000 tons/year polyformaldehyde construction---It seems that there are about 10 people on the construction site, and the pipe network has not yet been laid. There are no buildings at all, and the construction site is deserted.
Reply #42009-09-03
Does anyone have the latest news on the Henan Yongmei polyformaldehyde project?
Reply #52009-09-03
I wonder if you still remember Xiangtan Synthetic Chemical Plant?
Reply #62009-12-01
The first and second phases of the Yongmei polyformaldehyde 100,000 tons/year project have a total capacity of 40,000 tons. The civil construction has been basically completed, equipment has entered the site one after another, and the installation is about to begin in full. The product is expected to be released before October next year.
Reply #72009-12-01
The second phase is 60,000 tons. The preliminary work has been completed and the civil construction is expected to start in May next year.
Reply #82009-12-01
The situation mentioned by the comrade on the third floor also exists, because most of the personnel are working abroad* , and some personnel are busy with bidding and ordering, and there are only some construction management personnel on site.
Reply #92009-12-01
There are also Yongmei projects in Xinxiang City. Does anyone know what they are?
Reply #102009-12-03
“40,000 tons in the second phase”? Should it be "forty thousand tons in the first phase (60,000 tons in the second phase)"?
Reply #112012-12-21
Case title: If you are interested, please take a look at the dispute over the sales contract between the plaintiff Xiamen ABB Switch Co., Ltd. and the defendant Henan Capital Chemical Technology Co., Ltd.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.