Why must secondary grouting be carried out within 24 hours of leveling and alignment?

2019-05-16View Original

Thread Content

How is this time period defined and understood within 24 hours?
Reply #22019-05-17
What standard does the requirement come from? It’s probably to avoid failure in leveling due to some basic deformation or displacement occurring after an excessive interval of time
Reply #32019-05-17
This post was last edited by lovelife1997 on 2019-5-17 09:20, just to ensure accuracy. It can also be after 24 hours. But it is necessary to carefully re-check the equipment’s levelness and alignment and verify the data once again; doing this for particularly large and precision-based equipment is very troublesome and can delay the progress. So it is generally adjusted on the same day; secondary grouting must be carried out no matter how late it is, and the grouting has to be completed in one go, without being done in multiple stages. Companies and individuals specialized in equipment installation are all familiar with this procedure.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.