This post was last edited by Desert Fish on 2019-1-28 at 19:52. Maoming Petrochemical: Unit 2 of the high-pressure facility undergoes green and safe maintenance 2019-01-28 Source: Sinopec News Network. At 13:40 on January 24th, Unit 2 in the high-pressure workshop of Maoming Petrochemical’s chemical division began producing polyethylene with a grade of 2426K; the product quality met the required standards, enabling a successful start-up without any safety or environmental incidents. This planned shutdown for maintenance eliminated the risk of the unit’s second compressor operating under faulty conditions, laying a solid foundation for the facility to operate safely and at full capacity during the Spring Festival holiday, thus ensuring the achievement of the goal of starting operations successfully. This maintenance project consists of 22 main items and 36 sub-items. The work area on site is extensive and the operations involved are complex. The maintenance tasks include draining oil from the cylinders of each stage of the primary compressor, purging the gas lines that are leaking, replacing the bolts on the crankcase cover to eliminate leaks, reinstalling the outlet valves of stage 6, and reinstalling the tail rod of stage 6. Leak repair for the casing and oil pipelines of the secondary compressor ; Crankcase side panel replacement ; Oil injector maintenance (2478, 2472) ; Bolts for auxiliary pipelines of the secondary unit, clamping of pipe clamps; leakage correction at the cylinder block connections of 12A and 21A low-pressure systems ; Commissioning of bearing bush inspection system ; Numerous important maintenance tasks, including the reinstallation of 22 connecting rod crossheads, the handling of 10 high-pressure safety valves, and the calibration of the high-circulation high-pressure wax removal valve. The high-pressure workshop initiates the maintenance plan in advance, prepares the materials needed for maintenance, coordinates with relevant departments such as mechanical, electrical, and instrumentation teams regarding the maintenance tasks, breaks down these tasks according to their urgency and importance, sets specific time deadlines, and ensures systematic and organized management of all maintenance activities. Since the shutdown of the unit, the Party branch in this workshop established an HSSE supervision team composed of Party members and League members. In strict adherence to the \"six prohibitions,\" they strengthened safety and environmental management throughout the shutdown process, strictly controlled various emission indicators, ensured 100% recovery of materials from Unit 2, and achieved a shutdown with \"zero emissions.\" During maintenance operations, strict environmental protection requirements are implemented to ensure that \"no gases are released into the air, no dust falls to the ground, and no oil pollutants are discharged.\" Meanwhile, this workshop focuses on \"risk management\" and strictly adheres to HSSE management principles, controlling five key aspects: the planning stage, permit issuance, JSA analysis, information dissemination, and supervision. The workshop strictly controls the review of permits and tickets, holds JSA analysis meetings, ensures thorough three-level safety training for external workers, and imposes strict supervision and management on on-site supervisors. It has changed the practice of assigning supervisors with poor capabilities, instead assigning those who are most diligent and skilled to this role in order to ensure the safety of direct operations. By paying close attention to each stage of the work process, all aspects of on-site operations are kept under control, thereby effectively preventing accidents such as leaks, cross-contamination of materials, and conditions of excessive temperature or pressure. The HSSE supervision team composed of Party members and League members in the workshop conducts round-the-clock inspections 24/7, focusing on three aspects: the quality of maintenance work, safety during maintenance, and the safety of the maintenance personnel, in order to eliminate potential hazards from an early stage. The workshop safety team requires all employees to promptly identify and correct any violations in work procedures. It enforces strict supervision over the actual work processes, takes strict measures to curb behaviors that are risky, outdated, or defective. A quality inspection checklist is used for each maintenance task to ensure that the entire process remains safe and under control, with zero rework required for any task and no leaks at any maintenance point. This approach aims to achieve high standards and high-quality results in maintenance work, ensuring stable shutdowns, effective repairs, and smooth operations. (Liang Baowen)
Everyone is welcome to participate in the following series of sharing discussions; clicking on the link will take you there. -------------------------------------------------------------------------- This is a summary post for the 【Guess the Haichuan Equipment】 series – all Haichuan community members are encouraged to join in! https://bbs.hcbbs.com/thread-2079686-1-1.html (Source: Haichuan Chemical Industry Forum) Summary post for the 【Haichuan. Pioneers in the Chemical Industry】 series. https://bbs.hcbbs.com/thread-1842627-1-1.html (Source: Haichuan Chemical Industry Forum) Summary post for the 【In-depth Discussion on Modular Installation in Haichuan】 – everyone is welcome to participate in the discussion! https://bbs.hcbbs.com/thread-1773168-1-1.html (Source: Haichuan Chemical Industry Forum) The compilation posts of the 【Guess the Haichuan Food Items】 series are being updated continuously – with thousands of different foods, can you recognize them all? https://bbs.hcbbs.com/thread-2142205-1-1.html (Source: Haichuan Chemical Industry Forum) [Haichuan Chemical Industry Site] Compilation post on nitre caves – why did ancient people produce nitre in caves? ? https://bbs.hcbbs.com/thread-2145992-1-1.html (Source: Haichuan Chemical Industry Forum Website)
The maintenance of the crankcase in high-pressure compressors is a delicate task that requires high precision and expertise, with very stringent technical requirements.
I did some research – the concept of green maintenance was introduced by Europeans over a decade ago. Its origins lie in the design phase
Everyone is welcome to participate in the following series of sharing discussions; clicking on the link will take you there. -------------------------------------------------------------------------- This is a summary post for the 【Guess the Haichuan Equipment】 series – all Haichuan community members are encouraged to join in! https://bbs.hcbbs.com/thread-2079686-1-1.html (Source: Haichuan Chemical Industry Forum) Summary post for the 【Haichuan. Pioneers in the Chemical Industry】 series. https://bbs.hcbbs.com/thread-1842627-1-1.html (Source: Haichuan Chemical Industry Forum) Summary post for the 【In-depth Discussion on Modular Installation in Haichuan】 – everyone is welcome to participate in the discussion! https://bbs.hcbbs.com/thread-1773168-1-1.html (Source: Haichuan Chemical Industry Forum) The compilation posts of the 【Guess the Haichuan Food Items】 series are being updated continuously – with thousands of different foods, can you recognize them all? https://bbs.hcbbs.com/thread-2142205-1-1.html (Source: Haichuan Chemical Industry Forum) [Haichuan Chemical Industry Site] Compilation post on nitre caves – why did ancient people produce nitre in caves? ? https://bbs.hcbbs.com/thread-2145992-1-1.html (Source: Haichuan Chemical Industry Forum Website)
This concept has not yet been introduced to China; at least designers do not consider maintenance when designing.
Our mindset is still a bit outdated; at least that’s the case around me. Not to mention design, even during installation, maintenance is rarely taken into consideration. Of course, those responsible for installation also have their excuses: “I have to follow the design specifications when carrying out the work!” ” But I also said, why weren’t the brackets and hangers you installed made according to the design? Is the spacing elevation not in accordance with the design?