【Haichuan Civil Engineering Issues】With the wire conduits arranged in this way, what exactly is the problem at each stage?

2021-06-08View Original

Thread Content

[Sea River Civil Engineering Issues] With the wire conduits arranged in this way, what exactly went wrong at which stage?
Reply #22021-06-09
Is there no other better solution?
Reply #32021-06-09
Was this a requirement from the owner, a requirement from the designer, or just some random idea from the constructors?
Reply #42021-06-27
This is absolutely absurd; the design surely can’t be like this. It’s amazing that someone could damage the beams of the main building – at a level that’s comparable to that of children playing with building blocks; P
Reply #52021-06-29
When concealed mechanical and electrical pipes are installed in cast-in-place slabs, the outer diameter of the pipes should not exceed 1/3 of the slab thickness. Going through the beam is an even bigger mistake
Reply #62021-07-01
It damages the main structure, which is not good.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.