Concrete precast piles: how many meters can a pile driver drive in one day?

2021-08-28View Original

Thread Content

Concrete precast piles, with dimensions of 300x300 – how many meters can one pile driver drive in a day?
Reply #22021-08-28
That means one pile can be driven in two hours; including the time needed to move the pile driver, one shift per day should allow for 40 meters of progress
Reply #32021-08-28
Determine it yourself based on the pile length and the connection method
Reply #42021-09-04
Piling is carried out at a depth of 40 meters; at that time, 3 to 4 piles could be driven in 24 hours, depending on the conditions of the underground rock layers

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.