[History of Haichuan Pipeline] The longest hydrogen transmission pipeline "Baling-Changling" hydrogen pipeline

2021-11-04View Original

Thread Content

The "China Hydrogen Energy and Fuel Cell Industry White Paper" released by the China Hydrogen Energy Alliance in 2019 pointed out that the United States has 2,500 kilometers of hydrogen pipelines, Europe has 1,569 kilometers of hydrogen pipelines, and my country only has 100 kilometers of hydrogen pipelines. The total number of hydrogen pipelines worldwide is less than 4,500 kilometers, which is several orders of magnitude different from oil and gas pipelines. At present, low-pressure hydrogen pipeline transportation at home and abroad is still in the preliminary development stage. Cost is a factor restricting the development of hydrogen pipelines. Since hydrogen itself has a low volumetric energy density and is prone to "hydrogen embrittlement" on pipes, its pipeline transportation costs are often greater than the cost of natural gas pipeline transportation at the same energy flow rate. Data shows that in the United States, the cost of natural gas pipelines is only US$125,000-500,000/km, but the cost of hydrogen pipelines is approximately US$300,000-1 million/km, which is twice the cost of natural gas pipelines. my country's current hydrogen pipeline network is only 300-400km, and the longest hydrogen pipeline is the "Baling-Changling" hydrogen pipeline, with a total length of about 42km and a pressure of 4MPa. The construction scale of hydrogen refueling stations in China in 2019. From the first hydrogen refueling station put into operation in 2006 to the end of 2019, a total of 61 hydrogen refueling stations have been built in my country, of which 3 have been dismantled, 52 have been put into operation, and the number of hydrogen refueling stations under construction/planned is 72. Most of the hydrogenation stations built in my country from 2006 to 2015 are * * “The 863" project or the United Nations Development Program (UNDP) project to promote the commercial development of fuel cell vehicles in China mainly provides refueling services for fuel cell experimental vehicles and urban fuel cell public demonstration vehicles, but has not yet achieved commercial operation. The construction of hydrogen refueling stations began to accelerate after 2016, doubling from 2016 to 2018. The number of hydrogen refueling stations built in 2019 was twice that of 2018. The rapid growth trend is expected to continue. China's Hydrogen Energy Industry Production Capacity Forecast Analysis "China's Hydrogen Energy Industry Infrastructure Development Blue Book" predicts that by 2020, my country's hydrogen production capacity in the form of energy will reach 72 billion cubic meters, with 100 hydrogenation stations; 10,000 fuel cell vehicles; 50 hydrogen energy rail transit vehicles; and the total industry output value will reach 300 billion yuan. By 2030, the hydrogen energy industry will become my country's new economic growth point and an important part of the new energy strategy. The industrial output value will exceed 1 trillion yuan; the number of hydrogenation stations will reach 1,000, the number of fuel cell vehicles will reach 2 million, the construction mileage of high-pressure hydrogen long-distance pipelines will reach 3,000km, and the hydrogen energy industry infrastructure technology standard system will be nearly developed. * * At the same level, the development of hydrogen energy and fuel cell inspection and testing technology and the construction of service platforms form effective support for the development of the hydrogen energy industry.
Reply #22021-11-04
At about 6:30 pm on December 3, 2015, the longest long-distance hydrogen transmission pipeline under construction in China, the Baling Petrochemical "Baling-Chanling" hydrogen transmission pipeline, was successfully "pigged through the ball" from the first station to the distribution station and entered the production preparation stage. The Baling-Changling hydrogen transmission pipeline, with an investment of 190 million yuan, has a total length of 42 kilometers (including 24 kilometers from Yueyang City area to Yunxi area, and 18 kilometers from Yunxi area to Changling Refinery). Construction started in February 2012. It spans two districts of Yueyang City and 15 villages in Sixiang Town, and crosses 4 railways such as the Beijing-Guangzhou Line, 9 expressways and provincial roads, 3 rivers, and 8 directional drilling crossings. Due to the complex topography of the newly built hydrogen transmission pipeline, the medium hydrogen being transported has the characteristics of colorless, odorless, flammable, explosive and other characteristics. Clearing the remaining construction impurities in the pipeline, draining the water remaining in the pipeline during the hydraulic strength test and drying the pipeline to transport qualified hydrogen are key issues that must be solved to ensure safety before the pipeline is accepted and delivered for use.
Reply #32021-11-04
[History of Haichuan Pipeline] Summary post is constantly being updated to understand the development process of various pipelines https://bbs.hcbbs.com/thread-3068575-1-1.html (Source: Haichuan Chemical Forum)
Reply #42021-11-04
I was fortunate enough to participate in a hydrogen pipeline design case.
Reply #52021-11-05
Is it designed according to American standards? Does China have design standards? .
Reply #62021-11-08
Shanghai's Caowu hydrogen/synthetic gas pipeline from Huayi Wujing Base to Shanghai Chemical Industry Zone is more than 45 kilometers long and was completed and put into use in 2014.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.