【Major Chemical Equipment】085 – 56-inch ball valve for the China-Russia East Route (Heihe-Changling section) natural gas pipeline project

2022-04-04View Original

Thread Content

The past decade has been a period of rapid development in China’s chemical industry, marked by the emergence of many new processes, products, and equipment. There has also been significant progress in China’s chemical processing equipment, which has contributed to the swift advancement of the petrochemical sector. Here, we have compiled some of the achievements and breakthroughs made by Chinese equipment manufacturers in terms of larger-scale production and greater use of domestic equipment. We invite everyone to share their insights and discuss these topics together; let’s cheer for Made in China and support the development of chemical processing equipment! *********************************** Chengdu Chenggao Valve Co., Ltd. is the only valve manufacturer invited to attend the commissioning ceremony for the \"Development of Energy Cooperation along the China-Russia Eastern Route\" project. According to a announcement released by Chenggao Valves in September 2018, the company won the bid for the 56-inch ball valves and associated electric actuators under Package C1-2 of the gas pipeline project for the China-Russia East Line (Heihe-Changling section), with a total bid amount of 14.75 million yuan.
Reply #22022-04-11
The manufacturing quality is excellent – truly outstanding. Feel free to follow and engage in discussions about this series
Reply #32022-04-11
More people are welcome to participate in the relevant discussions. Click on the blue link to access it: The 【Haichuan Equipment Guessing Game】 series is being updated continuously in 2022; all Haiyu members are encouraged to join in! https://bbs.hcbbs.com/thread-2079686-1-1.html (Source: Huahai Chuanliu – Haichuan Chemical Industry Forum) Summary post on the series 【Major Equipment in the Chemical Equipment Industry】 https://bbs.hcbbs.com/thread-3312079-1-1.html (Source: Huahai Chuanliu – Haichuan Chemical Industry Forum) Summary post discussing the components of cracking furnace equipment for 【Ethylene Cracking】 https://bbs.hcbbs.com/thread-3308724-1-1.html (Source: Huahai Chuanliu – Haichuan Chemical Industry Forum)
Reply #42022-04-17
Construction of the Heihe-Changling section began with the start of the trial phase on June 29, 2015; accelerated construction was launched on December 13, 2017; and the construction tasks were fully completed on October 16, 2019~
Reply #52022-04-18
The reporter learned from Hebei Iron and Steel Group that the Heihe-Changling section of the China-Russia East Route natural gas pipeline project, which uses this batch of steel, operates in extremely harsh environmental conditions: it is located in a cold temperate continental monsoon climate zone, where temperatures can drop as low as minus 40 degrees Celsius; as a result, strict requirements are placed on the quality of the steel used for the pipe fittings.   To cope with low-temperature environments, the impact test temperature specified in the technical requirements for the X80 pipe fitting steel developed by Hebei Iron and Steel Group has been reduced from minus 30 degrees Celsius to minus 45 degrees Celsius. Meanwhile, the impact energy value has increased from a maximum of 70 joules to 135 joules, which is 95 joules higher than the maximum requirement specified in the standards – a level not seen before either domestically or internationally.   Furthermore, the diameter of 1422 mm, wall thickness of 57 mm, and minimum service temperature of minus 40 degrees Celsius for this batch of steel are all the highest standards for X80 long-distance pipelines in the global pipeline industry to date.   It is understood that during the supply period, HBIS Wugang, which was responsible for production, formed a project task force together with the customer. Based on the specific requirements of the project, they optimized and redesigned the composition of the steel plates as well as the production processes. After several rounds of trial production, they resolved the issue of unstable low-temperature toughness in the steel plates; all performance indicators met or exceeded the customer’s requirements, enabling stable large-scale supply and earning praise from the customer.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.