【Ten Years of Rapid Development in Chemical Equipment】744 – In 2022, a 4,000-ton crawler crane was used to lift the 1,723-ton propylene distillation tower for ExxonMobil’s first ethylene plant

2022-12-24View Original

Thread Content

Witnessing the ten-year rapid development of chemical processing equipment, we celebrate the prosperity and strength of modern China. Greater participation by everyone makes things even more exciting; with you here, Haichuan becomes even better. This is just a starting point – we welcome everyone to engage more actively in discussions on this forum. Replies will be rewarded, and discussions are encouraged. ------------------------------------------------- At 7:17 a.m. on December 21, 2022, accompanied by a whistle, the ExxonMobil Ethylene Phase I project team of Sinopec Transportation Company began lifting the Propylene distillation tower, the tallest and heaviest key equipment in this facility area. The tower was successfully lifted and placed in position at 12:10 p.m.
Reply #22022-12-24
【Ten Years of Great Development in Chemical Processing Equipment】Ongoing updates to the summary post; feel free to join the discussion: https://bbs.hcbbs.com/thread-3576046-1-1.html (Source: Haichuan Network – Chemical Industry Forum)
Reply #32022-12-24
ExxonMobil’s Propylene Distillation Column for Phase 1 of the ethylene plant is 103.2 meters tall, 8.7 meters in diameter, and weighs 1,723 tons; it is the largest and heaviest piece of equipment in this project. To ensure the safe, smooth, and successful completion of this lifting operation, the project team efficiently coordinated various resources; a 4,000-ton crawler crane was used as the main lifting device, while a 1,600-ton crawler crane was employed to assist with the lifting process. A thorough survey was conducted to determine the optimal route for the large cranes to enter the site ; Conduct safety and quality technical briefings for various professionals ; Safety verification of items such as construction plans, lifting points, lifting rigging, and crane machinery. Proper preparation in advance, including foundation treatment of the lifting site area, removal of obstacles, and coordination of construction activities, provided a solid foundation for the successful lifting of the equipment.
Reply #42022-12-24
The propylene distillation tower, which has been lifted into place, is 103.2 meters tall, 8.7 meters in diameter, and weighs 1,723 tons; it is the largest and heaviest piece of equipment in this project. To ensure the safe, smooth, and successful completion of this lifting operation, the project team efficiently coordinated various resources; a 4,000-ton crawler crane was used as the main lifting device, while a 1,600-ton crawler crane was employed to assist with the lifting process. A thorough survey was conducted to determine the optimal route for the large cranes to enter the site ; Conduct safety and quality technical briefings for various professionals ; Safety verification of items such as construction plans, lifting points, lifting rigging, and crane machinery. Proper preparation in advance, including foundation treatment of the lifting site area, removal of obstacles, and coordination of construction activities, provided a solid foundation for the successful lifting of the equipment.
Reply #52022-12-24
During the equipment lifting process, to meet the requirements for lifting the equipment, the 4000-ton main unit and the jacking mechanism need to move simultaneously: the main unit moves a distance of 14 meters, while the jacking mechanism rotates 120 degrees. The 1600-ton crawler crane needs to travel 57 meters while also transporting foundation boxes during its movement. In light of the long duration required for erecting the equipment, the project team carried out advance planning, made scientific arrangements, and organized everything meticulously. As a result, it took 4 hours and 53 minutes to safely and smoothly lift the propylene distillation tower to its installation location in just one go.
Reply #62022-12-25
Thank you for sharing; I’m not sure which region it is

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.