Thread Content
Witnessing the decade-long rapid development of chemical processing equipment, I admire the prosperity and strength of modern China. Wishing everyone a happy New Year, and may their families enjoy peace and health. I hope this contribution will inspire further participation from others; with your involvement, Haichuan becomes even better. Everyone is welcome to join in the discussions on this forum. ------------------------------------------------------------------The modernization project for the 15,000 t/a sulfur recovery unit at the PKOP Chimkent refinery in Kazakhstan was designed by the Southwest Branch of the Engineering Construction Co., Ltd.; it was installed on-site by CNPC Seventh Construction Company, with the equipment manufactured by the Equipment Manufacturing Branch of the same company. To adapt to the on-site construction conditions in Kazakhstan, this device features a modular design with independent system functions; it is manufactured and pre-assembled in China before being broken down into 28 individual modules for shipment to the project site. The total weight of the module is approximately 600 tons, of which the equipment weighs about 248 tons, the steel structure weighs about 282 tons, and the pipes weigh about 70 tons ; The total length of the pipelines is 2,821 meters, which corresponds to approximately 16,000 welds ; The cable length is approximately 23.5 kilometers, and there are about 240 sets of electrical and instrumentation equipment. The 15,000 t/a sulfur recovery unit for the modernization project of the PKOP Chimkent refinery in Kazakhstan was designed by the Southwest Branch of the Engineering Construction Co., Ltd.; it was installed on-site by CNPC No.7 Construction Company, while its manufacturing was carried out by the Equipment Manufacturing Branch of the same company.
To adapt to the on-site construction conditions in Kazakhstan, this device features a modular design with independent system functions; it is manufactured and pre-assembled in China before being broken down into 28 individual modules for shipment to the project site. The total weight of the module is approximately 600 tons, of which the equipment weighs about 248 tons, the steel structure weighs about 282 tons, and the pipes weigh about 70 tons ; The total length of the pipelines is 2,821 meters, which corresponds to approximately 16,000 welds ; The cable length is approximately 23.5 kilometers, and there are about 240 sets of electrical and instrumentation equipment.
The module project commenced on January 10, 2017; on September 7, 2017, the last shipment of products from the sulfur recovery unit in Kazakhstan’s PK facility was dispatched successfully. The project was completed two months ahead of schedule, and CNPC Seventh Construction Company achieved new results in its efforts to advance the \"Five Modernizations\" initiative.