With a lifting capacity of 4,366 tons, Huajin AAMEC’s largest single piece of equipment was lifted into place

2025-02-27View Original

Thread Content

This post was last edited by Desert Fish on February 27, 2025, at 13:06. At 10:43 on February 26, the raffinate tower, which is 118 meters tall, 15 meters in diameter, and has a lifting weight of 4,366 tons, was successfully installed at the Huajin Sinopec Aramco 2 million tons per year aromatic compounds complex, which is under the general contracting of Sinopec Guangzhou Engineering Co., Ltd. This achievement not only marks the successful installation of the largest single piece of equipment for this fine chemicals project but also sets new records for the highest height, largest diameter, and second-highest bare weight among similar equipment in this industry both domestically and internationally. Units such as CNPC First Construction, Sinopec Fourth Construction, and Qiyun Company are involved in the construction and installation work.
Reply #22025-02-27
The Huajin Sino-Aramco Fine Chemicals and Raw Materials Project, with a total investment of 83.7 billion yuan, is a comprehensive strategic cooperation project between China and Saudi Arabia signed and promoted under the witness of the leaders of both countries. The new facilities include 32 production units such as one with an annual refining capacity of 15 million tons, one for ethylene with an annual capacity of 1.65 million tons, and one for PX with an annual capacity of 2 million tons, along with supporting infrastructure.   Since the on-site construction began in March 2024, Sinopec Guangzhou Engineering Co., Ltd. focused on the critical path for the manufacturing and installation of the raffinate tower. By planning ahead, working closely with the client and the manufacturing unit, organizing tasks scientifically, innovating construction methods, and working overtime, it managed to complete the manufacturing of the raffinate tower in 196 days starting from the material cutting stage, setting a new record for the shortest delivery time for towers of this type. On January 19 this year, after the tower arrived at the site, faced with a tight schedule and heavy tasks, over 300 construction workers worked together without taking a break during the Spring Festival, braving wind and snow to carry out the installation of pipelines attached to the tower, platform escalators, supports and hangers, as well as lighting fixtures. This laid a solid foundation for the successful lifting of the entire tower and for it to be operational once the lights were installed.
Reply #32025-02-27
The raffinate tower is 118 meters tall and 15 meters in diameter, with a bare equipment weight of 3,500 tons. It is the tower of this type with the largest diameter, greatest height, and second-largest weight among chemical industry projects worldwide, and it is also the largest single piece of equipment in this project.
Reply #42025-02-27
Since the residue liquid tower arrived at the construction site on the evening of January 17, the builders began immediately on the urgent task of equipping the equipment and assembling the gantry crane on the 18th. Due to the tight schedule and heavy workload, 300 construction workers put aside their personal interests for the sake of the project; they gave up the opportunity to reunite with their families and take time off during the Spring Festival. Overcoming the challenges posed by heavy snow and cold weather, they continued with the construction work. After nearly 40 days of hard work, they successfully completed the installation of pipelines attached to the tower, platform escalators, and external insulation layers, as well as the assembly of a 5,000-ton gantry crane, thereby enabling the equipment to be used for lifting tasks. “After being fitted with clothing and covers, the tower structure weighed 4,366 tons. The lifting was carried out using the world’s most advanced and largest lifting equipment available – 5,000-ton gantry cranes and 4,000-ton crawler cranes – and it took 2 days to position the structure accurately, thus successfully fulfilling the lifting objectives. This solved the biggest challenge associated with installing such large equipment during the project construction, and it was of great significance for accelerating the project’s progress and ensuring the timely completion of the mechanical installations.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.