Thread Content
Dushan Energy’s PTA project has entered the final push phase: 2025-04-15 On March 28, 2025, the installation of the roof panels for the container replacement unit of the PTA-4 unit in Dushan Energy’s PTA project was completed, marking the entry of the project into its final push phase. The Dushan Energy PTA project is located in the Dushangang Economic Development Zone of Jiaxing City, Zhejiang Province. It includes two main production units, PTA-3 with an annual capacity of 4 million tons and PTA-4 with an annual capacity of 1.4 million tons, along with the associated utility systems. All of these were constructed and installed by the Construction and Installation Branch of Ningbo Engineering Company. Among them, Unit PTA-3 was put into operation on December 19, 2024, while Unit PTA-4 is expected to be completed in August this year. Shi Xiaqing, the PTA project manager at Dushan Energy, said that the ground installation work for Unit PTA-4 of the Dushan Energy project began last October; now the installation of the steel structure has been completed, the main instrument trays have been installed throughout the facility, and the installation of mechanical and electrical equipment as well as the construction of electrical trays have all entered a critical phase. During peak periods, there are over 1,700 workers on site. The project team will further optimize the construction organization, strengthen resource allocation, strictly monitor progress against deadlines, and prioritize quality and safety, striving with determination to meet the goal of completing the machinery installation by August.