Thread Content
On the morning of November 7th, local time, Module #6C of the heat absorption surface of the waste heat boiler in Singapore’s CCP50 600-megawatt combined cycle power plant project, which was constructed by China Power Construction, was successfully detached, marking the successful completion of the hoisting work for this boiler module. It is reported that this lifting operation involved 6 sets, totaling 18 modules, with the heaviest module weighing 245.521 tons; the total weight to be lifted was 3334.464 tons. Since its initiation on October 15, the entire lifting operation took 24 days. To ensure the smooth progress of the lifting operations, the project team developed a scientific and reasonable lifting plan and carefully planned the timeline. During the lifting process, professionals at all levels closely monitored each step, ensuring the successful completion of the lifting task.
[Common Issues in Haichuan Pipeline Design] – A compilation post; images and text are being updated. Feel free to join the discussion: https://bbs.hcbbs.com/thread-5705828-1-1.html (Source: Haichuan Chemical Forum (Hua Haichuan Liu hcbbs))
【Ten Years of Rapid Development in Chemical Equipment】The world’s largest seamless steel pipe production line, 2843-2025, was officially put into operation at Shandong Guangfu Group. https://bbs.hcbbs.com/thread-5705991-1-1.html (Source: Haichuan Chemical Forum (HCBBS))
【Ten Years of Rapid Development in Chemical Engineering Equipment】2844-2025: China’s first project for generating electricity from the residual pressure of high-pressure natural gas transmission pipelines – the Haimen Station natural gas residual pressure power generation project – has officially come online in Nantong, Jiangsu. https://bbs.hcbbs.com/thread-5706004-1-1.html (Source: Haichuan Chemical Industry Forum (HCBBS))
【Ten Years of Rapid Development in Chemical Engineering Equipment】The 2845-2025 2MW/600℃ ultra-high temperature heat pump energy storage demonstration project was successfully commissioned on its first attempt. https://bbs.hcbbs.com/thread-5706020-1-1.html (Source: Haichuan Chemical Engineering Forum (Hua Haichuan Liu hcbbs))
【Ten Years of Rapid Development in Chemical Engineering Equipment】The 2845-2025 2MW/600℃ ultra-high temperature heat pump energy storage demonstration project was successfully commissioned on its first attempt. https://bbs.hcbbs.com/thread-5706020-1-1.html (Source: Haichuan Chemical Engineering Forum (Hua Haichuan Liu hcbbs))
【Ten Years of Rapid Development in Chemical Equipment】2847-2025: The first domestically produced million-ton-scale methanol synthesis reactor passed the factory acceptance test https://bbs.hcbbs.com/thread-5706030-1-1.html (Source: Haichuan Chemical Forum (Hua Haichuan Liu hcbbs))
【Ten Years of Rapid Development in Chemical Equipment】2847-2025: The first domestically produced million-ton-scale methanol synthesis reactor passed the factory acceptance test https://bbs.hcbbs.com/thread-5706030-1-1.html (Source: Haichuan Chemical Forum (Hua Haichuan Liu hcbbs))
【HaiChuan Safety Discussion】Compilation of Hidden Dangers Around Us – Illustrated with photos and texts; everyone is welcome to participate in the discussion. https://bbs.hcbbs.com/thread-5705518-1-1.html (Source: HaiChuan Chemical Forum (HuaHaiChuanLiu hcbbs))
【HaiChuan Safety Discussion】Hidden Dangers Around Us – Direct discharge of condensate water from gas compressors in a certain workshop (a serious safety hazard) https://bbs.hcbbs.com/thread-5706461-1-1.html (Source: HaiChuan Chemical Forum (HuaHaiChuanLiu hcbbs))