[Haichuan Overseas Engineering] Installation of the first unit of the 4×1000kt sulfuric acid production plant supporting Indonesia’s KNI project with an annual nickel production capacity of 120,000 tons

2026-01-05View Original

Thread Content

This post was last edited by HaiChuan LaoYu on 2026-1-5 at 08:53. On January 1, 2026, the EPC project for the 4×1000kt sulfuric acid production units that are part of the KNI plant with an annual nickel production capacity of 120,000 tons – a project undertaken by China National Chemical Engineering Sixth Construction Corporation’s Indonesian branch – reached an important milestone: the first piece of equipment was successfully lifted, marking the official start of the equipment installation work for this project. On this New Year’s Day, the overseas project team of LiuHuaJian remained at the work site with a determination to go all out from the start. Under careful organization and precise guidance, they successfully completed the installation of the two exhaust gas absorption towers for Series 1 and 2 of the acid production facility in just 4 hours, in a safe and efficient manner. Each unit of this equipment weighs 45 tons, has a diameter of 6 meters, and a height of 25.7 meters. The installation was carried out using a combined lifting method involving a 150-ton crawler crane for the main lifting task and an 80-ton truck crane for assisting with the lifting process; this approach ensured safe and smooth execution of the lifting operations. Once completed, this sulfur-based sulfuric acid production facility will supply raw materials in a stable manner to the downstream high-pressure acid leaching smelting system, which is of great significance for ensuring the operation of the entire project and promoting the development of the local new energy battery material industry in Indonesia.
Reply #22026-01-05
[Common Issues in Haichuan Pipeline Design] – A compilation post; images and text are being updated. Feel free to join the discussion: https://bbs.hcbbs.com/thread-5705828-1-1.html (Source: Haichuan Chemical Forum (Hua Haichuan Liu hcbbs))
Reply #32026-01-05
The 【Haichuan Equipment Guessing】 series will continue to be updated in 2027 – all Haiyu friends are welcome to participate actively! https://bbs.hcbbs.com/thread-2079686-1-1.html (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))
Reply #42026-01-05
【Ten Years of Rapid Development in Chemical Engineering Equipment】China Petrochemical’s First Subcritical Once-Reheated Unit Successfully Commissioned 2952-2025 https://bbs.hcbbs.com/thread-5710462-1-1.html (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))
Reply #52026-01-06
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2025 to 2035, Chengdu Kene and other companies developed the world’s first megawatt-class fully liquid carbon dioxide energy storage system, which has been successfully put into operation for power generation. https://bbs.hcbbs.com/thread-5710545-1-1.html (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #62026-01-06
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2954 to 2025, Hengjiu Machinery has been engaged in research and development of carbon dioxide diaphragm compressors, which have contributed to the creation of the world’s first commercial supercritical carbon dioxide power generation unit, “Chao Tan Yi Hao”. https://bbs.hcbbs.com/thread-5710546-1-1.html (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #72026-01-07
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2954 to 2025, Hengjiu Machinery has been engaged in research and development of carbon dioxide diaphragm compressors, which have contributed to the creation of the world’s first commercial supercritical carbon dioxide power generation unit, “Chao Tan Yi Hao”. https://bbs.hcbbs.com/thread-5710546-1-1.html (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #82026-01-08
【Ten Years of Rapid Development in Chemical Processing Equipment】Sinopec’s fluidized-bed residue hydrogenation technology was applied for the first time in a million-ton-scale industrial plant from 2025 to 2957. https://bbs.hcbbs.com/thread-5710591-1-1.html (Source: Haichuan Chemical Forum (HCBBS))
Reply #92026-01-08
【Ten Years of Rapid Development in Chemical Processing Equipment】2958-2025: Maoming Petrochemical becomes the first company in China’s petrochemical industry to have its extruders monitored in real time; the project was approved successfully. https://bbs.hcbbs.com/thread-5710592-1-1.html (Source: Haichuan Chemical Forum (HCBBS))
Reply #102026-01-09
【Ten Years of Rapid Development in Chemical Processing Equipment】2959-2026 **Successful development of technology for keeping natural gas compressors operating without power interruption in pipeline systems** https://bbs.hcbbs.com/thread-5710632-1-1.html (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.