What is the sequence for acid cleaning, pressure testing, and oil filling of the lubricating oil pipeline?

2015-08-25View Original

Thread Content

This post was last edited by Young Builder on 2015-8-28 09:25. Generally speaking, pressure testing should be carried out first before cleaning and oil transportation, but should pickling be done before or after the pressure testing? Update: To prevent any confusion, the standard found is stated here: Pressure testing should be carried out after the pipeline has been flushed successfully. There is another standard: pickling and passivation should be carried out after the pressure test is successful. I’m dizzy too.
Reply #22015-08-25
It seems that pickling should be done before the pressure test
Reply #32015-08-25
In front. :Units with good handshake conditions. Replace the running oil with new one after the cleaning oil is used up.
Reply #42015-08-25
It seems that the stress test should be carried out before pickling.
Reply #52015-08-25
For pickling, temporary pipelines need to be connected; therefore, conducting a temporary pressure test after connection is a measure to ensure safety. After that, pickling is carried out, followed by alkali cleaning if necessary. The area is then rinsed with clean water, dried with compressed air, connected to the equipment, and finally lubricated.
Reply #62015-08-25
Proceed in the order of pressure test, pickling, and oil transportation
Reply #72015-08-28
This post was last edited by Young Builder on 2015-8-28 09:26. Pressure testing should be carried out after the pipes have been flushed successfully. There is another standard: pickling and passivation should be carried out after the pressure test is successful. I’m dizzy too.
Reply #82015-08-28
This post was last edited by li*nji on 2015-8-28 at 10:07. My understanding is as follows: 1: The pressure test should be carried out after the pipes have been flushed successfully; this flushing process involves cleaning the pipes to remove impurities, and it is mainly done using compressed air, water, and manual labor. It is a task that must be carried out after installation. 2: There is another standard: pickling and passivation should be carried out after the pressure test is successful. I’m confused too: pickling requires piping and pressure testing to be carried out, only after there are no leaks. These two requirements aren’t contradictory. Other tasks such as alkali cleaning, oiling, and pressure testing should be carried out as required
Reply #92015-08-28
By this “rinse,” I understand it to include purging, pickling, washing with water, etc.
Reply #102015-08-28
This cleaning does not include pickling; it is merely a purging process (water washing is generally not done either, as it is after all an oil pipeline).
Reply #112019-12-09
I think it should involve mixing components, spot welding, removing them for welding, applying hydraulic (or pneumatic) pressure, using hot air to clean the interior, performing acid washing and phosphating, assembling them onto the unit, flushing the pipes with oil, and concluding the process once the flushing is successful.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.