Energy consumption statistics and calculation in production workshops

2015-09-14View Original

Thread Content

Teachers, how is the energy consumption in your production workshops calculated? How is equipment wear and tear determined? What process is used for management? @liaifeng @liuquan1100 @sdwfsgyykai @wj821313389 @wlf1234 @ylb913 @3FCCtaofeng
Reply #22015-09-14
The last edit to this post was made by ylb913 on 2015-9-14 at 10:39. Previously, each workshop would report to the planning department the consumption or generation amounts of water (fresh water, circulating water, deoxygenated water, demineralized water, condensate water, heat transfer water) and gas (steam, fuel gas, nitrogen, air), while the electricity usage was reported by the electrical workshop. The measurement department also has relevant reports. There is also the amount of processing. The data obtained in the end represent a balanced state of the entire plant as planned, as well as a material balance; these data are then used to calculate the energy consumption of the equipment. ——But now with ERP and SMES systems in use, the processing volume and energy consumption are reported by the teams on a regular basis; however, they still need to be adjusted through balancing by the planning department.
Reply #32015-09-14
1. Previously, we had corresponding tables here; the DCS would perform calculations automatically based on those formats. There were specific conversion ratios for various types of energy and material consumption, which were used to determine the energy consumption value of the device. 2. More considerations are given to equipment wear and tear; basically, the service life and corrosion allowance are taken into account. 3. Nowadays, MES systems are used for management in all devices!
Reply #42015-09-20
I encountered a rather problematic situation: there is a workshop that produces three types of products, but there is no measurement for the various utility services used. When attempting to calculate costs, estimates have to be used for these aspects
Reply #52015-09-21
Without measuring equipment, estimation is the only option; it’s also possible to allocate costs based on different production volumes and output values

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.