A few minor issues with airtightness

2015-09-14View Original

Thread Content

1. How to make negative-pressure containers and pipelines airtight and how to detect leaks? 2. Do steam pipes and high-temperature pipes need to be inspected for leaks as they gradually heat up, and how are leaks detected?
Reply #22015-09-14
1: After the negative-pressure container and pipes are installed in place, a negative pressure of 120% of the operating pressure is applied, and the system is sealed. The changes in vacuum level can be observed directly using a vacuum gauge. It is generally specified that a loss of vacuum level of less than 10% within two hours is considered acceptable; if this criterion is not met, a leak detector is used to identify leaks. 2: Pressure testing is carried out on steam pipes and high-temperature pipes before operation; during the gradual heating process, manual inspections are conducted, and leak detectors are used to check for leaks
Reply #32015-09-14
Regarding negative-pressure pipelines and containers, it is recommended to check the design documents; generally, they should have a certain capacity to withstand positive pressure. Perform positive pressure airtightness testing within this range; once no leaks are detected, conduct negative pressure testing as a verification. Because using negative pressure for airtightness makes it impossible to locate the leak point. For steam pipes and high-temperature pipes, leak checks are generally carried out during the heating process. However, \"thermal tightening\" is also necessary: after reaching a certain temperature, heating is stopped, and all the connection bolts are thoroughly inspected and tightened one by one to prevent leaks.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.