Experts: Does anyone have the latest available information on the processes for new coal chemical projects? Please share it. Thank you! !
Reply #22016-12-08
1. Environmental Impact Assessment (1) Consultation opinions on the draft environmental impact assessment for the project; (2) Project environmental impact assessment report ; (3) Letter regarding the implementation standards for environmental impact assessment of the project ; (4) Approval of the environmental impact assessment report. 2. Plant location (1) Comments on the preliminary site selection for the project ; (2) Site selection report for construction project ; (3) Site selection opinion for project construction ; (4) Preliminary review opinions on land use for construction projects ; (5) Reply on the preliminary approval for project construction land by the Ministry of Land and Resources. 3. Water Resources (1) Project Water Resources Assessment Report ; (2) Review comments on the project’s water resources assessment report ; (3) Approval document for the water resources report from the provincial water resources department. 4. Safety Assessment (1) Safety Pre-assessment Report ; (2) Form for reviewing and filing the project safety assessment report ; (3) Approval document from the provincial safety department for the safety pre-assessment report. 5. Soil and Water Conservation (1) Soil and Water Conservation Plan Report ; (2) Expert group review comments on the project’s soil and water conservation plan ; (3) Approval Letter for Soil and Water Conservation Plan ; 6. Earthquakes (1) Report on the Seismic Safety Assessment of the Project Site ; (2) Review comments on the earthquake safety assessment report ; (3) Letter approving the seismic fortification requirements for the project site ; 7. Geological Disasters (1) Geological Disaster Risk Assessment Report ; (2) Registration Form for Filing the Project Geological Disaster Risk Assessment Report ; (3) Approval document for the geological disaster risk assessment report. 8. Request for Project Approval (1) Request from the Development and Reform Commission for project approval ; 9. Slag yard and utilization of ash and slag (1) Explanation of solid waste generated by the project ; (2) Commitment to the disposal of solid waste generated during the project’s production process ; (3) Commitment to the comprehensive utilization of solid waste generated during the project’s production process ; 10. Commitment to the treatment of wastewater generated during the project’s production process ; 11. Commitments regarding the construction of certain utility facilities in the project ; 12. Commitment to relocate residents from the proposed site for project construction ; 13. Reply to the report on applying for project approval for industrial park construction ; 14. Approval of the overall land use plan ; 15. Project Water Supply Commitment Letter ; 16. Letter of commitment regarding the supply of raw materials for the project ; 17. Commitment to power supply for the project ; 18. Letter of commitment regarding railway transport capacity (railway dedicated lines) ; 19. Letter of Agreement to Transfer Patent Technology ; 20. Certification Letter for the Evaluation of Scientific and Patent Technologies ; 21. Letter of intent for financing issued by the bank. It’s more or less the same.
Reply #32016-12-12
Thank you: handshake
Reply #42016-12-12
Is there anyone else who has more detailed information?
Reply #52016-12-12
Comrades on the second floor! ! ! A classmate*
Reply #62016-12-12
There should still be several reports missing, such as those on buried minerals, cultural relics, clearance requirements, **, etc
Reply #72016-12-12
There are numerous tasks in the early stages, as well as during design, construction, and commissioning, and this requires a concept of overall coordination
Reply #82017-10-09
Learn*:handshake

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.