Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is known as ( ). A. On-site acceptance upon delivery B. Acceptance at the time of pickup C. Acceptance upon receipt D. Acceptance upon warehousing 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is known as ( ). A, On-site acceptance
Reply #32015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is categorized as (A).
Reply #42015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is categorized as (A). A. On-site acceptance B. Delivery acceptance C. Receipt acceptance D. In-warehouse acceptance
Reply #52015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is categorized as (a).
Reply #62015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is classified as (A). A. On-site acceptance B. Delivery acceptance C. Receipt acceptance D. In-warehouse acceptance
Reply #72015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is categorized as (A). A. On-site acceptance B. Delivery acceptance C. Receipt acceptance D. In-warehouse acceptance
Reply #82015-11-13
Classified by the inspection method, the approach in which the purchaser of construction projects sends personnel to the supplier’s site to inspect the materials at the time of their production is classified as (A). A. On-site acceptance B. Delivery acceptance C. Receipt acceptance D. In-warehouse acceptance

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.