Let’s work on question 75-2015 from the 2015 First-Class Constructor Exam, specifically question 61 on Project Management. There will be a reward for those who answer it correctly. Those who do these questions every day are truly enthusiastic learners! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some questions from this year’s first-level constructor exam have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all the questions at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive rewards from the moderators. ****************************************** After completing the questions, it’s time to rest, and enjoying delicious food is the best way to do that. Everyone is encouraged to click on the posts related to food topics: a summary post of the “Food Search” series. Feel free to share your own ideas as well, and you’re also welcome to join discussions in the safety-related section. Fun posts about traffic violations – summary post*********************61. The “three synchronizations” required for construction cost accounting refer to the requirement that the value ranges of ( ) should be consistent. A. Progress of project implementation, output value statistics, actual costs B. Cost forecasting, cost planning, cost analysis C. Target cost, budgeted cost, actual cost D. Labor costs, material costs, machinery costs Correct answer: A
A. Progress status, output value statistics, actual cost
The “three synchronizations” required for the collection of construction cost accounting data refer to the fact that the value ranges of (a) should be consistent. A. Progress of work, output value statistics, actual costs. This question tests the calculation of construction costs. The image progress, output value statistics, and actual cost collection should be \"synchronized,\" meaning that their value ranges should be consistent.
61. The “three synchronizations” required for the accumulation of construction cost accounting refer to the fact that the value ranges of (A) should be consistent. A. Progress of projects, output value statistics, actual costs B. Cost forecasting, cost planning, cost analysis C. Target cost, budgeted cost, actual cost D. Labor costs, material costs, machinery costs
A. Progress of image development, output value statistics, actual costs
A. Progress of image development, output value statistics, actual costs