Let’s work on question 77-2015 from the First-Class Constructor Examination’s \"Project Management\" section – there is a reward for those who answer it correctly. Those who do these questions every day are truly eager learners! ! Today marks the start of the project management series – welcome to join! *************************************************I’ve gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to boost everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive rewards from the moderators. ****************************************** After completing the questions, it’s time to rest, and enjoying delicious food is the best way to do that. Everyone is encouraged to click on the posts related to food topics: a summary post of the “Food Search” series. Feel free to share your own experiences as well. You’re also welcome to join discussions in the safety-related section. Fun posts about traffic violations – summary post*********************63. The value of an international engineering contract is 50 million RMB, with a contract execution period of 300 days. The construction was carried out under the general contract of a domestic contractor; the total value of contracts awarded to this contractor during that period was 500 million RMB, while the company’s total management costs for the same period amounted to 15 million RMB ; Due to the owner’s design changes, the contractor requested a 30-day extension to the deadline. The amount claimed by this project department for headquarters management fees in the construction claim is ( ) ten thousand yuan. A 50 B15 C12 D10 Answer: B
B、15.--------1500*(5000/50000)=150-----150*(30/300)=15
The value of an international engineering contract is 50 million RMB, with a contract execution period of 300 days. The construction was carried out under the general contract of a domestic contractor; the total value of contracts awarded to this contractor during that period was 500 million RMB, while the company’s total management costs for the same period amounted to 15 million RMB ; Due to the owner’s design changes, the contractor requested a 30-day extension to the deadline. The amount claimed by this project department for headquarters management fees in the construction claim is (b) ten thousand yuan. B15
63. The value of an international engineering contract is 50 million RMB, with a contract execution period of 300 days. The construction was carried out under the general contract of a domestic contractor; the total value of contracts awarded to this contractor during that period was 500 million RMB, while the company’s total management costs for the same period amounted to 15 million RMB ; Due to the owner’s design changes, the contractor requested a 30-day extension to the deadline. The amount claimed by this project department for headquarters management fees in the construction claim is (B) ten thousand yuan. A 50 B15 C12 D10
63. The value of an international engineering contract is 50 million RMB, with a contract execution period of 300 days. The construction was carried out under the general contract of a domestic contractor; the total value of contracts awarded to this contractor during that period was 500 million RMB, while the company’s total management costs for the same period amounted to 15 million RMB ; Due to the owner’s design changes, the contractor requested a 30-day extension to the deadline. The amount claimed by this project department for headquarters management fees in the construction claim is ( ) ten thousand yuan. B15