At present, many private petrochemical enterprises adopt the E+P+C project contracting method, which places high demands on the project management skills and coordination abilities of the project managers on the owner’s side. For E+P+C projects, how can the owner ensure good construction quality control?
The owner needs to define the boundaries of responsibilities between themselves and the contractor, strive to have a say in matters, and ensure participation at every detail level in order to maintain strict control; the contractor will leave once the work is done and will not bear much responsibility
Led by the supervision company. But the most important thing is to understand the situation yourself; otherwise, it will be disastrous if you get tricked by those two companies together
Forget the supervisor; they can’t be relied on to do much, and their main role is just to sign documents.
The boundaries of responsibilities are specified in the contract, but these detailed aspects require effective management by the owner in order to be brought under control; it also demands a serious and responsible attitude serta active cooperation from the various professionals on the owner’s side. I would like to know how to carry out effective management
The various professionals from the owner’s side go to the construction site to monitor progress and check the construction quality.
These are basically the practices for larger projects these days. To be honest, based on my experience, working with well-known general contractors in China provides a certain level of reliability – they won’t act recklessly – which is much better than having no one specifically in charge on the part of the project owner. There’s no point in relying on the supervisor
The management requirements for the owner should be low, right? It’s much more difficult for the owner to handle PC projects; just for material management alone, hundreds of people are needed, and there are even more issues related to the construction itself. I think for the EPC project, the owner should keep a close eye on the progress, ensure proper oversight of the construction inspection processes, and handle the inspection and acceptance of equipment and materials upon their arrival. Too much interference from others really annoys the EPC team.
The E+P+C project involves the parallel contracting of E, P, and C: E is one entity, P represents procurement by the owner himself, and C is another construction company; it is not an EPC turnkey contract approach
Sign the contract, manage the supervisor properly, hold the construction unit accountable, and establish dedicated quality management and construction management departments
Finally it’s in a proper position, with such an explanation too.