【Daily Topic】【Engineering Version 20151223】

2015-12-23View Original

Thread Content

Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Which of the following statements about Gantt charts for progress planning is correct? A. A brief description of the tasks can be directly placed on the Gantt chart. B. Options for planning adjustments are available. C. It is possible to identify the critical path of the plan visually. D. The logical relationships between tasks are easy to clarify. [Production and Management Division] Seeking moderators and technical discussants to join
Reply #22015-12-23
Regarding the Gantt chart schedule, the correct statement is (A). A. A brief description of the tasks can be directly placed on the Gantt chart. B. Options for planning adjustments can be compared. C. The critical path of the plan can be identified visually. D. The logical relationships between tasks are easy to clarify
Reply #32015-12-23
Regarding the Gantt chart schedule, the correct statement is (A).
Reply #42015-12-23
Regarding the Gantt chart schedule, the correct statement is (A). A. A brief description of the tasks can be directly placed on the Gantt chart. B. Options for planning adjustments can be compared. C. The critical path of the plan can be identified visually. D. The logical relationships between tasks are easy to clarify
Reply #52015-12-23
A. The brief description of the work can be placed directly on the Gantt chart
Reply #62015-12-23
Regarding the Gantt chart schedule, the correct statement is (A). A. A brief description of the tasks can be directly placed on the Gantt chart. B. Options for planning adjustments can be compared. C. The critical path of the plan can be identified visually. D. The logical relationships between tasks are easy to clarify
Reply #72015-12-23
A. ---------------------
Reply #82015-12-23
Regarding the Gantt chart schedule, the correct statement is (A). A. A brief description of the tasks can be directly placed on the Gantt chart. B. Options for planning adjustments can be compared. C. The critical path of the plan can be identified visually. D. The logical relationships between tasks are easy to clarify

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.