Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. For a simply supported reinforced concrete beam with a span of 8 meters and a designed concrete strength grade of C40, the concrete strength must reach at least ( ) N/mm2 before the formwork at the bottom can be removed. A. 28 B. 30 C. 32 D. 34 Answer: B. 30
Reply #22016-01-09
B. 30. ---------------------------------------------
Reply #32016-01-09
For a reinforced concrete simply supported beam with a span of 8 meters and a designed concrete strength grade of C40, the formwork at the bottom can be removed only when the concrete strength reaches at least (B. 30) N/mm2.
Reply #42016-01-09
For a span of 8m, 75% of the strength is required; 40×75% = 30MPa.
Reply #52016-01-09
For a simply supported reinforced concrete beam with a span of 8 meters and a designed concrete strength grade of C40, the concrete strength must reach at least ( ) N/mm2 before the formwork at the bottom can be removed. A. 28 B. 30 C. 32 D. 34 Answer: (Correct answer) B. This question relates to the regulations regarding the quality management of concrete structure construction. For beams with a span of 8 meters, the concrete must reach 75% of its ultimate strength before the formwork can be removed; 40 × 75% = 30 MPa. Refer to page P439 of the textbook.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.