Thread Content
Installation methods for storage tanks: There are two methods for installing the main body of large vertical storage tanks – the normal installation method and the inverted installation method. The proper installation method involves using the bottom of the tank as the reference plane, with the tank wall panels being installed section by section, starting from the first section at the bottom. Inverted construction refers to using the bottom of the tank as the reference plane: first, the top ring wall plates and the tank roof are installed, after which the wall plates are assembled and welded from top to bottom in successive rings, alternatingly, until the bottom ring wall plates are installed. Most foreign construction companies use the normal installation method ; Domestic companies generally use the inverted method for vault storage tanks and the vertical method for floating roof storage tanks. 1. Installation method of vault storage tanks Vault storage tanks are the most common type of fixed-roof storage tanks, and the inverted installation method is widely used in China. In addition to being used for assembling certain special-structured vaulted storage tanks, the proper fitting method is rarely employed in the construction of ordinary vertical vaulted storage tanks. In practical applications, there are various methods of inversion lifting, including central column lifting, air jacking, manual chain block lifting, electric chain block group lifting, and hydraulic lifting. Currently, the more commonly used methods are manual chain hoist lifting and electric chain hoist group lifting for inversion, while hydraulic lifting for inversion is being gradually adopted. 2. Installation method of floating roof storage tanks The installation of large floating roof storage tanks with a capacity of 50,000 cubic meters or more is mainly carried out using the top-down installation method. Its advantages include the ability to make full use of large-scale lifting equipment, allowing for greater prefabrication depth; it is also easier to implement, which facilitates the adoption of automated welding techniques for such tanks. However, its disadvantages are the need for a large construction site, high technical complexity, numerous tasks that require working at heights, and associated safety risks. Construction companies also use the inverted construction method for large floating roof storage tanks of 20,000 cubic meters and below.
Inverted installation was also used for storage tanks with a capacity of over 50,000 cubic meters in the past, but an accident occurred in Xinjiang back then.
In our ten-year history as a company, we have never encountered something like this before. Shaanxi Ruite Thermal Engineering Mechanical and Electrical Equipment Technology Co., Ltd
Well, Yulong is currently under installation. This model comes with both a vaulted roof and an internal floating roof, but the normal installation method is used for those costing 10,000 or less, while the inverted installation method is used for those costing more than 10,000
Use inverted form for 10,000 and below, and normal form for above 10,000