Completion Notice for Pressure Pipelines

2016-03-30View Original

Thread Content

As the title suggests, in what form are the completion notices for pressure pipelines issued? Does the design unit send it directly to the Provincial Technical and Quality Supervision Bureau where the project is located?
Reply #22016-03-31
It is recommended to check the relevant requirements of the local quality inspection authorities, as these agencies have regulations regarding format and other aspects.
Reply #32016-03-31
This is generally arranged by the construction contractor, including providing notification of project commencement before work starts, and, after the construction is completed, notifying the special inspection agency to come to the site for supervision and inspection. Generally, construction companies have very good relationships with these departments; after all, these matters are originally the responsibility of the construction companies.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.