Installation of the flame arrester pipeline

2016-04-12View Original

Thread Content

This post was last edited by Clouds of flowing water shine on 2016-4-12 at 21:00. The fuel gas is sent for combustion; a flame arrester is installed. Some people say that to prevent the flame arrester from getting clogged, two flame arresters should be used in parallel, one in use and one as a backup. Isolation valves are installed at both the front and the back, and pressure gauges as well as vent valves are required as well. It ends up being more complicated than a control valve, and the main problem is that there isn’t enough space at the site. Is it really necessary?
Reply #22016-04-16
A bypass can be installed for the flame arrester, along with a rupture disc

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.