This post was last edited by hesonchang214 on 2016-5-12 at 16:34. Reward for participation: 2 Wealth. Reward for correct answer: 9 wealth. True or False: To ensure a tight bond between the upper and lower layers of concrete in layered pouring, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. Correct answer: Yes
Reply #22016-04-18
To ensure a tight bond between the upper and lower layers of concrete poured in layers, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. (Yes)
Reply #32016-04-18
To ensure a tight bond between the upper and lower layers of concrete poured in layers, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. ( Right )
Reply #42016-04-18
Correct,,,,,,,

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.