Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. In accordance with the Implementing Regulations of the Bidding Law, for projects that require project approval or authorization procedures in line with relevant regulations and for which bidding is mandatory by law, if the cost associated with open bidding constitutes a disproportionate proportion of the project’s contract value, it is possible to use invited bidding after obtaining approval from ( ). A. Departments responsible for project approval and authorization; B. Project owners; C. Engineering supervision units; D. Administrative departments in charge of construction. [Haichuan Thanksgiving] – Production Division. The Production and Management Division is seeking moderators and technical discussants to join us. Notice regarding the launch of the “I’m Saving Energy, Where Are You?” campaign in the petrochemical sector
Reply #22016-04-25
A, Department responsible for project approval and authorization
Reply #32016-04-25
My answer: D. . . . . . . . .
Reply #42016-04-25
A, Department responsible for project approval and authorization
Reply #52016-04-25
A, Department responsible for project approval and authorization
Reply #62016-04-25
A, Department responsible for project approval and authorization
Reply #72016-04-25
In accordance with the Implementing Regulations of the Bidding Law, for projects that require project approval or authorization procedures in line with relevant regulations and for which bidding is mandatory by law, if the cost associated with open bidding constitutes a disproportionate proportion of the project’s contract value, it is possible to use invited bidding after approval from (A). A. Departments responsible for project approval and authorization B. Project owner C. Project supervision unit D. Administrative department in charge of construction affairs
Reply #82016-04-25
A, Department responsible for project approval and authorization

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.