What is the basis for using a method of laying the communication cables of the control system one day per layer?

2016-05-10View Original

Thread Content

What is the basis for using a method of laying the control system communication cables one day per layer? Are there corresponding regulatory requirements?
Reply #22016-05-10
Doing it day by day, step by step, is to increase reliability and stability; it can also be considered a form of redundancy
Reply #32016-05-10
I know that, but is there any evidence for it? Is it just *habit?
Reply #42016-05-10
General provisions for instrument and control engineering design
Reply #52016-05-10
Isn’t that the enterprise standard of Sinopec? Are there any generic standard-type ones?
Reply #62016-05-11
There is no mandatory requirement, but this approach does have its advantages, as it reduces the likelihood of network fibers being damaged simultaneously. It is mainly the fibers for CCR and FAR that require such path redundancy, and the investment remains acceptable

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.