Issues with hydraulic testing and airtightness testing

2016-07-06View Original

Thread Content

This post was last edited by “一路风景一路歌” on July 6, 2016, at 15:07. For the qualification upgrade of Units D1 and D2 to Category A2, the basic drawing data specifies both the pressure for hydraulic testing and that for airtightness testing. Should both types of tests be conducted during manufacturing, or is it sufficient to perform just one of them? I’m using drawings from another source; if I don’t understand them well, I hope the teachers can give me some guidance. Design pressure: 1.77 MPa; Hydrostatic test pressure: 2.32 MPa; Airtightness test pressure: 1.77 MPa
Reply #22016-07-06
There is another question: since we are developing this product for upgrading purposes, is it still necessary to include a product name plate? Personally, I think it’s not necessary to obtain them (the plaque manufacturing licenses D1 and D2); I’m not sure if this is correct. Please give me some guidance.
Reply #32016-07-06
Do both: conduct a pressure test first, then a airtightness test.
Reply #42016-07-06
Thank you! Who can answer the second question?
Reply #52016-07-06
LPG storage tanks — both types need to be installed.
Reply #62016-07-18
The hydraulic test is a type of pressure resistance test, while the airtightness test is a type of leakage test; they are two different inspection methods with distinct focuses. The specifications require that both be carried out. (When leakage tests must be conducted is clearly stated in the relevant regulations; for example, in the case of extremely or highly hazardous media, even trace leaks are not allowed, etc.)
Reply #72016-07-18
As for the product nameplate, it can be made, but the device must pass the evaluation before final inspection and release from the factory; at that point, I think the nameplate should indicate the A2 certification.
Reply #82016-07-19
Both pressure testing and airtightness testing must be carried out. The product nameplate also needs to be properly prepared and installed on the equipment.
Reply #92016-07-27
Both need to be done: one is the pressure test, and the other is the leak test.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.