Participation reward: 2 Wealth. Reward for the correct answer: 9 wealth. For a certain construction process that requires on-site supervision, the time interval from the moment the construction party notifies the supervision company’s on-site supervision team in writing until the start of work on that process should be at least ( ). A. 12 hours B. 24 hours C. 36 hours D. 48 hours Correct answer: B
Reply #22016-09-30
For a certain construction step, on-site supervision is required; the time interval between the date when the contractor notifies the supervision company’s on-site supervision team in writing and the start of work on that step should be at least (B). A. 12 hours B. 24 hours C. 36 hours D. 48 hours
Reply #32016-09-30
For a certain construction step that requires on-site supervision, the time interval from the moment the contractor notifies the supervision company’s on-site supervision team in writing until the start of work on that step should be at least (B. 24 hours).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.