What reports are required from a third-party authoritative agency for the commissioning of a boiler?

2016-12-25View Original

Thread Content

With the boiler about to be put into operation, what certification reports showing compliance with performance standards, issued by third-party authoritative agencies, does the boiler manufacturer need to provide? In which specific time periods?
Reply #22016-12-25
The pressure vessel inspection report must be provided at the time of shipment.
Reply #32016-12-25
The pressure vessel inspection report is provided by the boiler factory; what I need is an inspection report issued by a third-party testing agency
Reply #42016-12-26
Installation inspection report issued by the local boiler inspection agency
Reply #52016-12-26
The installation supervision inspection report may also require a water quality analysis report
Reply #62016-12-26
Which department provides the water quality analysis report?
Reply #72016-12-26
Is the boiler installation supervision inspection report issued after the boiler’s hydrostatic test or at the acceptance stage?
Reply #82016-12-26
The boiler installation supervision and inspection report is issued by the installation supervision and inspection agency (usually a special inspection institute) after the boiler installation is completed and the installation contractor submits the completion documents to this agency; it is issued certainly after the hydrostatic test. As for whether a water quality analysis report is required and who can issue it, one can consult the installation supervision and inspection agency. In addition, a safety valve calibration report and a pressure gauge verification report are also needed – those can be issued by those who have the appropriate qualifications; if not, one should consult the installation supervision and inspection agency
Reply #92016-12-26
Water quality analysis reports are usually issued by the boiler inspection agency along with the boiler inspection results
Reply #102016-12-26
Obtain the installation supervision inspection report and apply for a usage registration certificate; for pipelines under pressure, flaw detection is also required

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.