HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Questions regarding the inspection of pipes and pipe fittings

2021-11-16View Original

Thread Content

According to the specifications for the construction and acceptance of petrochemical and national standard pipelines, it is required that for chromium-molybdenum alloy steel, nickel-containing low-temperature steel, molybdenum-containing austenitic stainless steel, nickel and nickel alloys, titanium and titanium alloys, as well as zirconium and zirconium alloys – pipes and pipeline components – verification tests for the main alloying metal elements shall be carried out using spectral analysis or other methods, with the test results documented in a test report. However, all these materials are provided by the Party A and are taken from Party A’s warehouse; they are not purchased by the construction party on its own for use in the construction work. Therefore, which party should be responsible for the inspection of these materials, and who shall bear the associated costs?
Reply #22021-11-16
It has nothing to do with which supplier is used; things are done in accordance with the regulations, and fees are charged based on those same regulations
Reply #32021-11-16
The specifications do not specify who is responsible for carrying out this task; should it be done by the construction company itself or by the purchasing party? The purchasing unit should have a verification procedure for the materials upon their arrival, before storing them
Reply #42021-11-16
You can ask the purchasing department to do it; the relevant documents need to be provided to you as handover materials
Reply #52021-11-17
SH/T3501: This clause. . Place it under Arrival Inspection. . So whoever is responsible for the arrival inspection will do it. . GB/T20801: Before use. So it is the installation unit that is responsible for GB 50235: before use. Then it is the installation unit that is responsible

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.