This post was last edited by yuchenchf on 2017-5-3 16:28. Reward for participation: 2 Wealth. Correct reward: 6 wealth. Regarding the implementation of construction schedules and their role, which of the following statements are correct? ( ) A. It is possible to determine the annual funding requirements for the project. B. It is possible to determine the specific schedule for the construction work. C. It is prepared based on a control-oriented construction schedule. D. It is possible to determine the schedule targets for the milestone events. E. It is possible to validate the project’s schedule targets. BC
This post was last edited by Lantian on 2017-4-28 10:07 bc
Regarding the implementation of the construction schedule plan and its role, the correct statements are ( BC ). A. It is possible to determine the annual funding requirements for the project. B. It is possible to determine the specific schedule for the construction work. C. It is prepared based on a control-oriented construction schedule. D. It is possible to determine the schedule targets for milestone events. E. It is possible to validate the project’s schedule targets
Regarding the implementation of the construction schedule plan and its role, the correct statements are ( BC ). A. It is possible to determine the annual funding requirements for the project. B. It is possible to determine the specific schedule for the construction work. C. It is prepared based on a control-oriented construction schedule. D. It is possible to determine the schedule targets for milestone events. E. It is possible to validate the project’s schedule targets