HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

【Daily Question】Utilities – Civil Engineering – 20190506

2019-05-06View Original

Thread Content

This post was last edited by hesonchang214 on 2019-5-6 07:06. What are the correct principles for preparing a construction project organization plan?   a. Try to avoid using formal construction methods to prevent pollution and damage.
b. Completing all preparatory work for construction at once can save costs.
c. Integrating it with construction project management.
d. It is necessary to arrange construction in phases, so that the facilities can be put into operation or delivered for use gradually.
Answer: c
Analysis: The relevant principles are:
(1) Strictly abide by the time schedules set forth in the contract as well as the deadlines for completing the project and delivering it for use. Construction should be carried out in phases according to production needs, with corresponding facilities put into operation or delivered for use. It is essential to ensure that each completed set of projects can function independently, and that the main projects are completed simultaneously with the relevant auxiliary projects. (2) Reasonably arrange the construction procedures and sequence.   ①The relevant construction preparatory work should be completed in a timely manner, either all at once or in phases; ② During actual construction, the site should first be leveled, utility networks laid, roads constructed, and other site-wide works as well as permanent structures usable for construction carried out, before proceeding with the construction of individual projects; (3) Make use of existing facilities, whether original or those located nearby, as much as possible to reduce the need for temporary structures; (4) Integrate this approach with project management.   For a system in a small business or a large construction project, due to a short construction period or the requirements of the production process, it is not necessary to build it in phases; it can be constructed and put into operation all at once.
Reply #22019-05-06
d. It is necessary to arrange construction in phases, with corresponding commissioning or delivery for use
Reply #32019-05-06
c. Integration with construction project management

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.