The perimeter of the top surface of the concrete foundation in contact with the machine base should be larger than the machine base by ( ) mm.    A. 100  B. 150  C. 200  D. 250  Answer: C
Reply #22019-10-26
C. 200. It should be determined based on the actual conditions of the equipment; it should be at least greater than () mm
Reply #32019-10-26
The perimeter of the top surface of the concrete foundation, where the basic structure and materials come into contact with the machine base, should be 150 mm larger than the machine base itself.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.