This post was last edited by Zhizhi Ming on 2024-5-12 at 11:28. The major maintenance has begun; it involves the maintenance of the threaded lock ring heat exchanger in the hydrogenation unit, which is a type of U-tube heat exchanger. The steps are as follows: preparation work → making marks on the shell and head assembly → measuring the distance from the end face of the threaded lock ring to the cover plate of the tube box, as well as the distance from it to the end face of the shell → removing the clamping bolts on the head assembly → recording the residual torque → installing clamping plates and counterweights → removing components such as the threaded lock ring from the head assembly → removing the inner and outer pressure rings → removing the sealing disc → removing the gasket on the tube side → removing the inner sleeve and support ring → making marks on the end faces of the inner flange assembly and the partition box → measuring the distance from the triple-ring assembly to the end face of the partition box → removing the bolts of the inner flange → recording the residual torque → removing the triple-ring assembly → removing the inner flange → removing the upper cover plate and gaskets of the tube box, as well as the packing and packing cover → removing the partition box → removing the tube bundle, cleaning it, conducting physical and chemical tests, and performing pressure testing → removing the gasket on the shell side, checking the sealing surfaces → cleaning → conducting physical and chemical tests inside the shell.
Reply #22024-05-12
The installation steps are as follows: preparation work → installation of the shell-side gaskets → installation of the tube bundle → installation of the packing and packing gland → installation of the baffle box → installation of the inner flange → installation of the triple ring → installation of the inner flange bolts (measuring the distance from the triple ring to the end face of the baffle box) → airtightness check and pressure testing of the shell side → installation of the gaskets and the upper cover of the tube box → installation of the inner sleeve → installation of the tube-side gaskets → installation of the sealing disk → screwing in the head cover assembly (measuring the distance Lb from the end face of the threaded locking ring to the end face of the housing) → tightening of the outer ring compression bolts (measuring the distance La from the end face of the threaded locking ring to the end face of the tube box cover) → installation of the inner ring compression bolts → airtightness check and pressure testing of the tube side → completion of the work.
Reply #32024-05-12
Thank you for sharing; kudos to Chinese chemical technology
Reply #42024-05-19
It’s really clean – was it cleaned with a high-pressure washer?
Reply #52024-05-19
Obviously, the last image shows the new device
Reply #62024-05-19
The last image shows the new core that has been replaced.
Reply #72024-05-20
Cleaning the tube bundle is a key step in core pulling. Water or a suitable cleaning agent, along with a soft brush or high-pressure water gun, can be used to thoroughly remove dirt and deposits from within the tube bundle. After cleaning, the tube bundle must be rinsed repeatedly until the water or solution flowing out is clear and free of dirt. Finally, check whether the tube bundle is clean; if necessary, repeat the cleaning steps.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.