Judgment: In soils with a high permeability coefficient and abundant groundwater, the pipe well dewatering method should be given priority. ( ) Answer: Correct
Reply #22020-07-10
Correct. Wellpoint dewatering methods include light wellpoints, electroosmotic wellpoints, jet wellpoints, pipe wellpoint systems, and deep wellpoint systems. (1) When the foundation pit is deep and the groundwater level is high, multiple stages of dewatering wells are required when using light well points ; (2) When the dewatering depth exceeds 8 m, jet well points are advisable; the dewatering depth can reach 8–20 m ; (3) In soil layers with a high permeability coefficient and large groundwater levels, tube well dewatering is advisable ; (4) When the precipitation depth exceeds 15 m, and ordinary submersible pumps and centrifugal pumps used in tube well dewatering systems are insufficient to meet the dewatering requirements, the depth of the tube wells can be increased, and deep well pumps, or deep well dewatering systems, can be employed instead.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.