Compressor replacement

2017-03-28View Original

Thread Content

The compressors in the light hydrocarbon recovery unit fail the replacement tests time and again – what could be the reasons? Let’s discuss it together!
Reply #22017-03-28
The valve cannot be fully closed; there are dead ends in the replacement process; the replacement time is insufficient; the measures taken are incomplete
Reply #32017-03-28
The valve has leakage points, the number of replacement cycles is insufficient, and the purity of the replacement gas is not adequate.
Reply #42017-03-28
There are dead corners; there are leakage points! Fewer replacement times!
Reply #52017-03-28
Is it the air in the displacement system or the combustible gas within it that is displaced? The ends and low points must be drained completely. Performing pressure-driven replacement yields better results.
Reply #62017-03-28
Replace with flammable gas. What is pressure-driven replacement? Experts, please advise
Reply #72017-03-28
There must be dead corners; it took over ten days of replacement work as required before it was handed over. . .
Reply #82017-03-28
Here, we carry out separate replacement for the first and second stages of the compressor; the first stage passed the test, but the second stage did not. It’s likely not a problem with the purity of the gas used for replacement
Reply #92017-03-28
Pressurize the system with nitrogen; once the pressure reaches a certain level, shut it off. Then discharge several times from the ends, blind spots, etc., until the pressure drops to the lowest level. Test the combustible gas content again after several replacements.
Reply #102017-03-29
It’s still because the dead corner hasn’t been fully replaced. It is recommended that the poster use nitrogen under certain pressure to carry out continuous displacement along the process for a period of time first, before increasing the pressure for further displacement.
Reply #112017-03-29
It is a continuous displacement process~~One can use the method of pressurization – holding – depressurization, repeating this cycle of displacement~~

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.